Tarmac cement and lime Aberthaw OM3 Fibre backbone network installation

Tarmac cement and lime Aberthaw OM3 Fibre backbone network installation

June 2019
Tarmac

Installation of fibre backbone to various plant electrical switch rooms to allow network connectivity to digital electrical supply metering.

Supply and installation of:

OM3 Fibre Network Infrastructure Installation.

9No. OM3 8 Fibre Multimode SWA LSZH cable links between M/O Cab – ESSA, ESSA-ESSR31, ESSR31-ESSF2, ESSF2ESSJ, ESSJ-ESSR29, ESSR29-ESSE, ESSE-ESSR30, ESSJESSC & ESSC-M/O Cab.

8No. 12U 600mm x 600mm wall cabinet 19″ rack c/w with 4U blanking plates for din rail to be mounted to. 4″ Galvanised Medium Return Tray will be installed, internally in ESSRs from cable entry point to cabinet location.

Externally to building cladding or building struture where required if no existing containment or structure is available to secure cables.

Access equipmet MEWPs and MSTs for high level work. All fibre will be fusion spliced to LC presentation panels and tested to TIA industry standard using Fluke DSX versiv analyser.